E-distribución requested COL GROUP to provide a first movable container primary station equipped with a 24kV/2000A switchboard, which supplies electricity to the newly built industrial and commercial areas in the outskirts of Seville, Spain, using remote monitoring features.

COL GROUP’s solution allows e-distribución to provide 16,000 users with electricity, improving energy efficiency and grid management.

The project was overlooked by COL GROUP throughout all its phases – from planning, to consultation and testing.

The movable container was integrated and tested directly in our factory and then on site.

The status of MV panels and LV circuit breakers, energy related values and numerous other variables can be monitored remotely at any time, and used to detect and rectify any irregularities that may occur.